ASCOT MINING PLC

A PLUS-quoted
Company

Market Status:

Open

Symbol Cncy Code Bid Offer Mid Ann Volume Last Traded 52W Low 52W High
ASMP GBX 16.00 19.00 17.50 16000 02/09/2010 15 46

CompanyASCOT MINING PLC
ISINGB00B2QH7M99/GBX/PLUS-exn
SourceCIS
HeadlineAssay Results and Operations Update
Released07:00AM 8th April 2010
NumberCIS.20100407:BIT:2558:0:Ascot Mining plc






Ascot Mining Plc

                       ASSAY RESULTS AND OPERATIONS UPDATE

London, 8 April 2010, Ascot Mining (Ascot" or the "Company) (PLUS Markets: ASMP,
XETRA(R): AM3.DE) is pleased to provide this update to its  Chassoul  and  Tres
Hermanos / El Recio mining and processing operations:

Chassoul Mine and Mill:

The  first raise (a vertical opening) connecting the lower Cajeta tunnel to  the
upper  tunnel  was successfully completed, allowing immediate access  to  higher
grade  material,  facilitating  development  of  the  ore  block  and  improving
ventilation on the lower level. The South and the North walls of the raise  were
sampled every meter and assayed, the results are appended. A second raise  of  a
total of 8 planned will access ore between the two levels in the Cajeta vein.
With  the  exception  of  a  few isolated areas the  ground  is  very  competent
requiring very limited support. Mining will be via stope and crown pillar,  with
subsequent  pillar  recovery, thus minimizing dilution. The Company  intends  to
reclaim  the  tailings  from the tailings pond and pump them  underground  after
adding Portland cement. There is no danger of pollution and this method of  back
filling is a standard procedure in many mines.

The  mill circuit is functioning well after the completion of a number of  small
changes as recommended by the Company's Senior Metallurgist. The laboratory  was
completed and provides timely assay results. An immediate expansion of  manpower
will  permit a 24 hour seven days per week operation to deal with the increasing
demand  for sample analysis associated with the underground activities  and  the
exploration program.

The  bigger  ball mill is scheduled to be moved into place within  10  days  and
connected to the circuit. Depending on the hardness of the ore and metallurgical
characteristics the recently announced expansion of capacity of the mill will be
150  tons per day. The ore from the Boston concession, which is scheduled to  be
processed at Chassoul until the first gravity mill is in operation, has not been
tested  for  millability  since the vein was only  recently  uncovered  and  ore
extraction is about to commence.

Assay results:

The  following  assays were obtained in the raise between the  lower  and  upper
Cajeta tunnels on the Chassoul property.

Assay results         
Raise between lower and upper Cajeta tunnels
Note: values in gm/ton, width in cm

Sample      South     North    widthS    widthN      Grade xm S       Grade xm N
1m          6         2        95        120         570              240
2m          4         4        90        80          360              320
3m          4         6        125       50          500              300
4m          8         4        120       72          960              288
5m          8         4        95        80          760              320
6m          6         2        95        77          570              154
7m          6         2        110       115         660              230
8m          10        5        130       80          1300             400
9m          11.67     15       90        50          1050.3           750
10m         6         4        80        63          480              252
11m         14        4.67     60        50          840              233.5
12m         6         13.33    30        30          180              399.9
13m         4         4        20        20          80               80
14m         16        4        25        56          400              224
15m         26        14.67    20        63          520              924.21
16m         8         8        60        22          480              176
17m         11.33     6        25        50          283.25           300
18m         10.67     9        44        60          469.48           540
19m         3.33      8.33     36        45          119.88           374.85
20m         2.67      6.67     50        50          133.5            333.5
21m         6         8.33     55        50          330              416.5
22m         10        19.33    87        80          870              1546.4
23m         10.33     5.33     70        70          723.1            373.1
24m         9         38.33    67        90          603              3449.7
25m         7         19       52        67          364              1273
26m         6         11.67    74        180         444              2100.6
27m         13        8        85        86          1105             688
28m         7.33      8.33     70        70          513.1            583.1
29m         8         2        65        57          520              114
30m         16.67     9.33     68        65          1133.56          606.45
31m         43.33     4.67     70        70          3033.1           326.9
32m         5.33      3.33     62        88          330.46           293.04 

                               2225      2206        20685.73         18610.75
                                                    
average     0.2989    0.2713   oz/ton        
  
average     9.3       8.44     gm/ton                       
 
Notes: The numbers 2225 and 2206 represent the sum total of the individual width of the vein at the sample point on the
South and North wall of the raise respectively.
The numbers 20685.73 and 18610.75 represent the product sum total of the individual assay multiplied by
the width of the vein at the sample point on the South and North wall. The average grade of the South wall is obtained
by dividing 20685.73 by 2225 to obtain 9.30gm/ton or 0.2989oz/ton. Similarly the  average grade of the North wall is
18610.75 divided by 2206 is 8.44gm/ton or 0.2713oz/ton. The foregoing 
assays were obtained at the Company's new onsite laboratory.
 
 
Supplementary Ore Supply:

Arrangements have been made to truck ore with a grade of +9g/t from Las Juntas to Chassoul commencing 
immediately. This will ensure that the plant can operate at full capacity if the Chassoul mine, while
continuing with mine development, cannot supply sufficient ore to operate at full capacity. This will
ensure full utilization of plant capacity. Ore from Las Juntas will be stockpiled at Chassoul and processed separately
once approximately 300 tons have been accumulated.
 
Mr. Andrew von Kursell, P.Eng., Ascot's COO states "Production for the first three months of 2010 fell  short of our
target due to a number of unrelated events. Processing was interrupted due to changes that  were made to the leach
circuit to convert from a batch operation to a continuous process; a delay in  carbon delivery from Mexico forced a mill
shut down, a crusher break down required a 5 day mill shut    down, and a delay in obtaining a governmental permit to
use an alternate explosive supplier forced a
cessation of all mining activity underground resulting in a shortage of ore being delivered to the mill.  As of April 1,
all short comings have been corrected; the surface ore stockpile is being increased to 
ensure the mill does not run out of feed again".
 

Tres Hermanos:
 
The municipality has approved the development of a gravity mill. The environmental report is expected to 
be completed this week and will be submitted to the Government for approval. Once approval is received  construction of
the gravity mill will commence.

The mine, referred to as Marvin's finka (farm) has been rehabilitated and, subject to reinstallation of service lines,
is ready to resume production of ore. Once production starts, a raise (a vertical  opening) will be driven in ore to
surface. The purpose of this raise is twofold, one is to improve  ventilation, and secondly to access 20 to 24 gm/ton
gold bearing material (0.64 to 0.77 oz/ton). Based on current information, the average grade of ore to be mined is 11
gm/ton (0.35 oz/ton) with high grade  pockets.

The gravity mill, consisting of a crusher, screen, ball mill, Humphry spirals and/or a Long Tom sluice   box, will
upgrade the ore to produce a concentrate which will be shipped to the Chassoul mill or be 
processed in Las Juntas. No chemicals are used to produce the concentrate.

Depending on the efficiency of the plant the tailings will either be stored for further processing or  mixed with
Portland cement and pumped underground to fill old workings. The plant will be built to have  a daily capacity of 75
tons/day, but will initially operate at 10 tons/day until the circuits are  balanced. When stabilized, the plant will
operate at full capacity.
 

Revised Production Target:

As a result of the unforeseen loss of La Toyota and resulting delays in the expansion at Chassoul projected production
to September 2010 has been revised from 28,000 ounces to approximately 20,000  ounces. While a setback, this adjustment
is not considered to be of longer term significance as the  Company is aggressively moving forward with its development
and acquisition plans.
 
                         
                  The Directors take responsibility for this announcement.
 
Enquiries: Damien Daly +44 (0) 7880 55 46 47
         
     Email: info@ascotmining.com
     Website: www.ascotmining.com